Western Sydney Airport Standalone Facilities – Command Centre

SCG’s scope included coordinating with the client, their appointed design consultants and Design & Construct contractors to:

  • Develop three phases of security services design (30%, 60%, 90%) for the site  
  • Provide SCEC advisory and design services  
  • Update the cost plan and program (from that submitted at the Request for Tender stage)  
  • Manage stakeholder reviews and engagement (focused on the end users) across multiple Government Border Force Agencies  
  • Manage relevant approvals to expedite delivery  
  • Provide tender support services during the construction phase  

Provide construction management services, including SCEC oversight and witness and acceptance testing of electronic security systems plus final inspections.